Data Center Capacity Expansion for Los Angeles (BUR)
Data Center Capacity Expansion for Los Angeles (BUR)
22 April 2026, 11:30 UTC
22 April 2026, 11:30 UTC
Fastly will be adding capacity at our Los Angeles (BUR) POP. End-users may observe connection resets as traffic is migrated onto new hardware starting on 22 April 2026 at 11:30 UTC.
Our estimated duration is 4h.
When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please verify that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team at https://support.fastly.com.
22 April 2026, 15:30 UTC
22 April 2026, 15:30 UTC
The scheduled maintenance has been completed.