Data Center Capacity Expansion for London (LHR)

Maintenance
17 April 2026, 03:00 UTC

Data Center Capacity Expansion for London (LHR)

Status: closed
Start: 16 April 2026, 23:00 UTC
End: 17 April 2026, 03:00 UTC
Duration: 4 hours
Affected Components:
Platform Europe London (LHR)
Update

16 April 2026, 23:00 UTC

16 April 2026, 23:00 UTC

Fastly will be adding capacity at our London (LHR) POP. End-users may observe connection resets as traffic is migrated onto new hardware starting on 16 April 2026 at 23:00 UTC.

Our estimated duration is 4h. 

When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please verify that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team at https://support.fastly.com.

Resolved

17 April 2026, 03:00 UTC

17 April 2026, 03:00 UTC

The scheduled maintenance has been completed.