Fujairah (FJR) with Possible Impact

Incident
08 September 2025, 22:50 UTC

Fujairah (FJR) with Possible Impact

Status: in progress
Start: 06 September 2025, 12:00 UTC
Affected Components:
Platform Asia Fujairah (FJR)
Affected Groups:
All Public Users
Investigating

06 September 2025, 12:00 UTC

06 September 2025, 12:00 UTC

We're investigating possible performance impact affecting the Fujairah (FJR) data center.

We are aware of an issue with a third party subsea cable impacting performance in the surrounding region.

All other locations and services are unaffected.

Identified

06 September 2025, 17:07 UTC

06 September 2025, 17:07 UTC

Our engineers are aware of an issue with a third party subsea cable impacting performance to our Fujairah (FJR) data center.

Users may experience increased latency and errors.

All other locations and services are unaffected.

Monitoring

08 September 2025, 22:50 UTC

08 September 2025, 22:50 UTC

We are continuing to monitor the impact caused by a reported cable cut, and our status page will remain in monitoring mode until all services are fully restored and we have a period of sustained stability. Customers may continue to see intermittent errors impacting services routed through the Fujairah (FJR) Point of Presence (POP).

This event has not caused any impact to Fastly products, and our ability to provide network and security services to all other POP locations remains unaffected by this incident. Our engineers are closely monitoring the situation to ensure all services are restored as soon as the repairs have been completed.

We will provide a final update to our status page once we have confirmation that all services have been fully restored.