Retrospective: Impacted Performance in Mumbai (BOM)
Informational
22 July 2025, 01:40 UTC
Retrospective: Impacted Performance in Mumbai (BOM)
Status: closed
Date:
22 July 2025, 00:50 UTC
End:
22 July 2025, 01:40 UTC
Duration: 50 minutes
Affected Components:
Platform
Asia
Mumbai (BOM)
Affected Groups:
All Public Users
Monitoring
22 July 2025, 00:50 UTC
22 July 2025, 00:50 UTC
Fastly Engineers detected a performance impacting event affecting the Mumbai (BOM) data center.
All other data centers and services were unaffected. The issue has been resolved and we are monitoring performance closely.
Resolved
22 July 2025, 01:40 UTC
22 July 2025, 01:40 UTC
This incident has been resolved.
To offer feedback on our status page, click "Give Feedback"