Data Center Capacity Expansion for Mumbai (BOM)

Maintenance
22 July 2025, 01:00 UTC

Data Center Capacity Expansion for Mumbai (BOM)

Status: closed
Start: 21 July 2025, 19:00 UTC
End: 22 July 2025, 01:00 UTC
Duration: 6 hours
Affected Components:
Platform Asia Mumbai (BOM)
Affected Groups:
All Public Users
Update

21 July 2025, 19:00 UTC

21 July 2025, 19:00 UTC

Fastly will be adding capacity at our Mumbai (BOM) POP. End-users may observe connection resets as traffic is migrated onto new hardware starting on 21 July 2025 at 21:00 UTC.

Our estimated duration is 6h. 

When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please verify that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team at https://support.fastly.com.

Resolved

22 July 2025, 01:00 UTC

22 July 2025, 01:00 UTC

The scheduled maintenance has been completed.

To offer feedback on our status page, click " Give Feedback