Data Center Capacity Expansion for Phoenix (PHX)

Maintenance
07 June 2025, 02:30 UTC

Data Center Capacity Expansion for Phoenix (PHX)

Status: closed
Start: 06 June 2025, 22:30 UTC
End: 07 June 2025, 02:30 UTC
Duration: 4 hours
Affected Components:
Platform North America Phoenix (PHX)
Affected Groups:
All Public Users
Update

06 June 2025, 22:30 UTC

06 June 2025, 22:30 UTC

Fastly will be adding capacity at our Phoenix (PHX) POP. End-users may observe connection resets as traffic is migrated onto new hardware starting on 06 June 2025 at 22:30 UTC.

Our estimated duration is 4h. 

When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please verify that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team at https://support.fastly.com.

Resolved

07 June 2025, 02:30 UTC

07 June 2025, 02:30 UTC

The scheduled maintenance has been completed.