Retrospective: Impacted Performance in Tokyo (NRT)

Informational
15 January 2025, 07:25 UTC

Retrospective: Impacted Performance in Tokyo (NRT)

Status: closed
Date: 15 January 2025, 07:15 UTC
End: 15 January 2025, 07:25 UTC
Duration: 10 minutes
Affected Components:
Platform Asia Tokyo (NRT)
Affected Groups:
All Public Users
Monitoring

15 January 2025, 07:15 UTC

15 January 2025, 07:15 UTC

Fastly Engineers detected a performance impacting event affecting the Tokyo (NRT) Point of Presence (POP) for Compute services.

All other data centers and services were unaffected. The issue has been resolved and we are monitoring performance closely.

Resolved

15 January 2025, 07:25 UTC

15 January 2025, 07:25 UTC

Engineering has confirmed that Tokyo (NRT) POP for Compute services has been fully restored. Customers may have experienced a brief period of manage.fastly.com being inaccessible from 07:15 to 07:25 UTC.

This incident is resolved.


To offer feedback on our status page, click "Give Feedback

Status Post, Created Date/Time: 0001-01-01 00:00:00 UTC 



Note: Our Customer Escalation Management team will update the start date and time of the initial "investigating" status post upon the resolution of this incident. This update is meant to provide our customers and their end users with a potential impact window. The date and time mentioned in the message above indicates when the status post was requested by our Acute Incident Response team.