Data Center Capacity Expansion for Newark (EWR)
Data Center Capacity Expansion for Newark (EWR)
15 August 2024, 03:30 UTC
15 August 2024, 03:30 UTC
Fastly will be adding capacity at our Newark (EWR) POP. End-users may observe connection resets as traffic is migrated onto new hardware starting on 15 August 2024 at 03:30 UTC.
Our estimated duration is 7h.
When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please verify that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team (support@fastly.com).
15 August 2024, 10:30 UTC
15 August 2024, 10:30 UTC
The scheduled maintenance has been completed.