Lima (LIM) Data Center Capacity Expansion

Maintenance
28 November 2023, 11:00 UTC

Lima (LIM) Data Center Capacity Expansion

Status: closed
Start: 28 November 2023, 07:00 UTC
End: 28 November 2023, 11:00 UTC
Duration: 4 hours
Affected Components:
Platform South America Lima (LIM)
Affected Groups:
All Public Users
Update

28 November 2023, 07:00 UTC

28 November 2023, 07:00 UTC

Fastly will be adding capacity at our Lima (LIM) POP. End-users may observe connection resets as traffic is migrated onto new hardware starting on 28 November 2023 at 07:00 UTC.

Our estimated duration is 4h. 

When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please verify that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team (support@fastly.com).

Resolved

28 November 2023, 11:00 UTC

28 November 2023, 11:00 UTC

The scheduled maintenance has been completed.