Frankfurt (FRA) Data Center Capacity Expansion

Maintenance
17 May 2023, 02:00 UTC

Frankfurt (FRA) Data Center Capacity Expansion

Status: closed
Start: 16 May 2023, 22:00 UTC
End: 17 May 2023, 02:00 UTC
Duration: 4 hours
Affected Components:
Platform Europe Frankfurt (FRA)
Affected Groups:
All Public Users
Update

16 May 2023, 22:00 UTC

16 May 2023, 22:00 UTC

Fastly will be adding capacity at our Frankfurt (FRA) data center. End-users may observe connection resets as traffic is migrated onto new hardware, starting on 16 May 2023 at 22:00 UTC.

  • Our estimated duration is 4h

In order for customers who use this POP as an Origin Shield to leverage new cache nodes for an expanded cache footprint, customers can either apply a new config version at a time of their choosing, or their shielding configuration will be updated on their behalf 7 days after this maintenance window closes. 

When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please be sure to check that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team (support@fastly.com).

Resolved

17 May 2023, 02:00 UTC

17 May 2023, 02:00 UTC

The scheduled maintenance has been completed.