Capacity Expansion: Madrid (MAD)
Capacity Expansion: Madrid (MAD)
29 July 2022, 23:06 UTC
29 July 2022, 23:06 UTC
Fastly will be adding capacity at our Madrid, Spain (MAD) data center. End-users may observe connection resets as traffic is migrated onto new hardware. When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please be sure to check that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team (support@fastly.com).
03 August 2022, 15:47 UTC
03 August 2022, 15:47 UTC
In order for customers who use this POP as an Origin Shield to leverage new cache nodes for an expanded cache footprint, customers can either apply a new config version at a time of their choosing, or their shielding configuration will be updated on their behalf 7 days after this maintenance window closes. When this change is applied, customers may observe additional origin traffic as new cache nodes retrieve content from origin. Please be sure to check that your origin access lists allow the full range of Fastly IP addresses (https://docs.fastly.com/en/guides/accessing-fastlys-ip-ranges). Customers with any questions or concerns should contact Fastly’s Support team (support@fastly.com).
03 August 2022, 22:00 UTC
03 August 2022, 22:00 UTC
Maintenance will begin as scheduled in 60 minutes.
03 August 2022, 23:00 UTC
03 August 2022, 23:00 UTC
Scheduled maintenance is currently in progress. We will provide updates as necessary.
04 August 2022, 08:18 UTC
04 August 2022, 08:18 UTC
The scheduled maintenance has been completed.